History of Projects
 


Color Construction Logo.JPGCOMPLETED CAPITAL IMPROVEMENT PROJECTS 1997-06


§       ADA COMPLIANCE

West End Middle, Hume Fogg High, M.L. King Magnet, Pearl-Cohn High 

Architect: Larry Woods & Associates

Contractor: Shankle-Lind, LLC

Scope: Bring Schools to ADA Compliant

Total Cost: $5,624,793
Completion: November 2004

§        ADA IMPROVEMENTS AT ADMINISTRATION BUILDING

Architect: Larry Woods & Associates

Contractor: SES Construction, LLC

Scope: Admin. Building ADA Compliance

Total Cost: $864,082

Completion: April 2006

 

§       AIR CONDITION MIDDLE SCHOOL GYMS (6 SCHOOLS)

Antioch Middle, Donelson Middle, Kennedy Middle, McMurray Middle, Two Rivers Middle, and Wright Middle

Engineer: NJC, Incorporated

Contractor: Anderson Piping

Scope: Install air conditioning systems in Gyms

Total Cost: $599,189

Completion: August 2003

§        AIR CONDITION MIDDLE SCHOOL GYMS PKG. "B"(3 SCHOOLS)
H.G. Hill, Brick Church, and Dalewood Middle Schools

Engineer: 3-D Engineering

Contractor: Advanced Mechanical

Scope: Install air conditioning systems in Gyms

Total Cost: $488,000

Completion: September 2005

 

§      AMQUI ELEMENTARY SCHOOL

Architect: Oxford Architecture

Contractor: Shankle-Lind, LLC

Scope:  New Building

Capacity:  652

Space/Student: 122.25 sq. ft.

Area:  79,708 sq. ft.

Total Cost:  $6,118,000.00

Cost/Square Foot:  $76.76

Completion:  September 2000

§      ANTIOCH MIDDLE SCHOOL

Architect: R. Chris Magill

Contractor: Price-Davis Construction, Inc.

Scope:  Modernization

Capacity:  809

Space/Student: 164

Area:  132,476 sq. ft.

Total Cost:  $1,113,335.75

Cost/Square Foot: $8.40

Completion: August 2000


§     
BAILEY MIDDLE SCHOOL

Architect: Maxwell Johanson Maher

Contractor: Robert S. Biscan Company

Scope:  Modernization and addition (24 classrooms)

Capacity:  719

Space/Student: 135 sq. ft.

Area:  97,000 sq. ft.

Total Cost:  $5,663,000.00

Cost/Square Foot: $58.38

Completion:  August 2001

§      JERE BAXTER MIDDLE SCHOOL

Architect: Southeast Venture

Contractor: R.G. Anderson Company

Scope: Addition/Cafeteria Expansion (12 Classrooms)

Capacity: 756

Space per Student: 148 sq. ft.

Area: 21,658 sq. ft.

Total Cost: $1,799,000

Cost per Square Foot: $83.00

Completion: March 2004

§      BELLSHIRE ELEMENTARY DESIGN CENTER SCHOOL

Architect: Hastings Architecture

Contractor: J. Harold Shankle Company

Scope: Addition 15 classrooms and P.E.

Capacity:  514

Space/Student: N.A.

Area:  24,165 sq. ft. addition

Total Cost:  $1,482,688.00

Cost/Square Foot: $61.36

Completion:  June 1998

 

§      BORDEAUX ENHANCED OPTION SCHOOL

Architect: Pitts & Associates

Contractor: R.G. Anderson Company

Scope: Addition and Renovation (19 classrooms, P.E. Room, and Kitchen addition)

Capacity: 300

Space/Student: 212.5 sq. ft.

Area: 63,744 sq. ft.

Total Cost: $2,986,000

Cost/Square Foot: $10.49

Completion: November 2004

 

§      BRICK CHURCH MIDDLE SCHOOL

Architect: E&H Architects, P.C.

Contractor: Robert S. Biscan Company

Scope:  New Building

Capacity:  652

Space/Student: 138 sq. ft.

Area:  89,830 sq. ft.

Total Cost:  $7,350,000.00

Cost/Square Foot:  $81.84

Completion:  August 2001

 

§      BROOKMEADE ELEMENTARY SCHOOL

Architect: Community Tectonics

Contractor: Mirsaidi Construction

Scope:  Addition and Renovation 11 classrooms and P.E. Room

Capacity:  375

Space/Student: N/A

Area:  20,662 sq. ft. addition

Total Cost:  $1,797,945.00

Cost/Square Foot:  $87.00

Completion:  January 2001

 

§      BUENA VISTA ENHANCED OPTION ELEMENTARY SCHOOL

Architect: Hinson Miller Kickirillo

Contractor: Robert S. Biscan Company

Scope: Addition and Renovation

Capacity: 400

Space/Student: 163 sq. ft.

Area: 65,355 sq. ft.

Total Cost: $4,191,000

Cost/Square Foot: $64.13

Completion: October 2003


§         CALDWELL ELEMENTARY SCHOOL

Architect: Community Tectonics

Contractor: Shankle-Lind, LLC

Scope: Addition and Renovation

Capacity: 600

Space/Student: 104 sq. ft.

Area: 62,212 sq. ft.

Total Cost: $3,975,158

Cost/Square Foot: $634.90

Completion: August 2005

 

§      CAMERON MIDDLE SCHOOL

Architect: Kline Swinney Associates

Contractor: Robert S. Biscan Company

Scope: Modernize existing building

Capacity: 850

Space/Student: 148 sq. ft.

Area: 125,699 sq. ft.

Total Cost: $4,237,000

Cost/Square Foot: $33.70

Completion: August 2003 

 

§      CARTER LAWRENCE ELEMENTARY MAGNET SCHOOL

Architect: Facilities Design Group

Contractor: Robert S. Biscan Company

Scope: New Elementary School

Capacity: 500

Space/Student: 131 sq. ft.

Area: 65,800 sq. ft.

Total Cost: $5,574,679

Cost/Square Foot: $84.72

Completion: July 2004

 

§      CHARLOTTE PARK ELEMENTARY SCHOOL

Architect: Larkin Group

Contractor: Alexander & Shankle

Scope:  Add 10 classrooms and PE Room, Renovate offices

      Capacity:  688 (Total School)

      Space/Student: N/A

      Area:  21,000sq. Ft.

      Total cost:  $1,350,962.00

      Cost/Square Foot:  $75.05

Completion:  January 2003


§         I.T. CRESSWELL ARTS MAGNET MIDDLE SCHOOL

Architect: Hastings Architecture Associates

Contractor: Robert S. Biscan Company

Scope: New Arts Magnet Middle School

Capacity: 600

Space/Student: 184 sq. ft.

Area: 110,405 sq. ft.

Total Cost: $10,729,675

Cost/Square Foot: $97.18

Completion: July 2006

 

§      CROFT MIDDLE DESIGN CENTER SCHOOL

Architect: Gould Turner Group Architecture

Contractor: Robert S. Biscan Company

Scope: New Middle School

Capacity: 800

Space/Student: 138 sq. ft.

Area: 110,000 sq. ft.

Total Cost: $8,609,053

Cost/Square Foot: $78.26

Completion: July 2003

 

§      DALEWOOD MIDDLE SCHOOL

Architect: Hastings Architecture

Contractor: Robert S. Biscan Company

Scope:  Renovation and Addition (49 Classrooms and Gym)

Capacity:  832

Space/Student: 130.72 sq. ft.

Area:  109,000 sq. ft.

Total Cost:  $6,646,652.00

Cost/Square Foot:  $60.98

Completion:  July 2002 

 

§      DONELSON MIDDLE SCHOOL

Architect: Gresham Smith & Partners

Contractor: Alexander & Shankle

Scope: Addition/Renovation (43 Classrooms and Gym)

Capacity:  742

Space/Student: 151.6 sq. ft.

Area:  112,489 sq. ft.

Total Cost:  $6,163,367.00

Cost/Square Foot:  $54.79 (includes new and renovation sq. ft.)

Completion:  November 2000

 

§      DUPONT ELEMENTARY SCHOOL

Architect: Pitts & Associates

Contractor: Romach, Incorporated

Scope: Addition 6 classrooms and P.E./office

Capacity: 454

Space/Student: N/A

Area: 16,000 Sq. Ft. additions

Total Cost:  $1,096,000.00

Cost/Square Foot:  $68.50

Completion:  March 2000


§         DUPONT HADLEY MIDDLE SCHOOL

Architect: Fowlkes & Associates

Contractor: Robert S. Biscan Company

Scope: Addition & Renovation

Capacity: 600

Space/Student: 177 sq. ft.

Area: 106,348

Total Cost:  $3,100,000

Cost/Square Foot:  $29.15

Completion:  May 2005

 

§         EAKIN ELEMENTARY SCHOOL

Architect: Earl Swensson Assoc.

Contractor: Shankle-Lind, LLC

Scope: Addition & Renovation

Capacity: 500

Space/Student: 207 sq. ft.

Area: 103,730

Total Cost:  $9,366,130

Cost/Square Foot:  $90.29

Completion:  October 2006

 

§      JOHN EARLY MIDDLE PAIDEIA MAGNET SCHOOL

Architect: Thompson Architectural Group

Contractor: Medical Construction Group

Scope:  New Building

Capacity:  629

Space/Student: 146 sq. ft.

Area:  91,989 sq. ft.

Total Cost:  $6,809,000.00

Cost/Square Foot:   $74.02

Completion:  July 2002

 

§      CONVERT OLD JOHN EARLY BUILDING TO MCGRUDER FAMILY RESOURCE CENTER

Architect: Adkisson Harrison & Associates

Contractor: Metropolitan Nashville Public Schools Maintenance Department

Scope:  Replace broken windows, install carpet, bring building up to current codes, repair water damage, and paint throughout.

Total Cost: $250,000

Completion: August 2003 

 

§      EAST LITERATURE MAGNET SCHOOL

Architect: Street Dixon Rick Architecture

Contractor: Doster Construction Company

Scope: Modernization

Capacity: 1,300

Space/Student: 160 sq. ft.

Area: 208,300 sq. ft.

Total Cost: $8,216,180

Cost/Square Foot: $39.44

Completion: August 2004


§         EAST LITERATURE MAGNET ATHLETIC FIELD

Architect: SSOE, Inc.

Contractor: Bruce Adams Construction

Scope: Rough grading athletic field

Total Cost: $638,276

Completion: September 2005

 

§      THOMAS A. EDISON ELEMENTARY SCHOOL

Architect: E&H Architects, P.C.

Contractor: Turner Universal

Scope: New Elementary School

Capacity: 600

Space/Student: 117 sq. ft.

Area: 70,225 sq. ft.

Total Cost: $7,197,301

Cost/Square Foot: $102.48

Completion: July 2004

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS (2 SCHOOLS)

Granbery Elementary and Andrew Jackson Elementary

Architect: Adkisson Harrison & Associates

Contractor: Bruce Adams Construction

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $593,000.00

      Completion: August 2003


§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

      JT Moore Middle

Architect: SSOE, Incorporated

Contractor: R.G. Anderson Company

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $540,775.00

Completion: August 2003

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

      Kings Lanes Design Center

Architect: SSOE, Incorporated

Contractor: CSMC, Incorporated

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $322,052.00

Completion: August 2003 

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

DuPont Hadley Middle School

Architect: Hastings Architecture

Contractor: Bruce Adams Construction

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $97,000.00

Completion: August 2003

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

Dodson Elementary and Apollo Middle

Architect: Hastings Architecture

Contractor: Bruce Adams Construction

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $200,299.00

Completion: August 2003

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

Fall Hamilton

Architect: Adkisson Harrison & Associates

Contractor: CSMC, Incorporated

Scope: Construct walls at open areas to create classrooms.

Total Cost: $1,167,318

Completion: June 2004

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

Glencliff Elementary

Architect: Hastings Architecture

Contractor: RCR Building Corporation

Scope: Construct walls at open areas to create classrooms.

Total Cost: $1,058,391

Completion: June 2004

 

§      FALL HAMILTON ENHANCED OPTION ELEMENTARY SCHOOL

Architect: The Larkin Group

Contractor: Shankle-Lind, LLC

Scope: Addition 10 classrooms and PE

Capacity:  314

Space/Student: N/A

Area:  23,000 sq. ft.

Total Cost:  $1,655,000.00

Cost/Square Foot:  $71.96

Completion:  June 2000

 

§      GLENDALE ELEMENTARY SCHOOL 

Architect: Barge Waggoner Sumner & Cannon

Contractor: R.G. Anderson Company

Scope: Addition and Modernization

Capacity: 400

Space/Student: 130 sq. ft.

Area: 28,900 existing, 23,000 new sq. ft.

Total Cost: $3,127,000

Cost/Square Foot: $60.13

Completion: July 2004

 

§      GLENGARRY ELEMENTARY SCHOOL

Architect: SSOE, Incorporated

Contractor: Fitzgerald Construction

Scope: Addition (6 classrooms, PE Room, and Kitchen Addition)

Capacity: 300

Space/Student: 83.33 sq. ft.

Area: 25,000 sq. ft.

Total Cost: $1,596,643

Cost/Square Foot: $63.87

Completion: July 2004


§         GLENVIEW ELEMENTARY SCHOOL

Architect: Hart Freeland Roberts

Contractor: R.G. Anderson Co. Inc.

Scope: New Building

Capacity: 500

Space/Student: 134 sq. ft.

Area: 67,000 sq. ft.

Total Cost: $7,009,061

Cost/Square Foot: $97.96

Completion: August 2006

 

§      GOODLETTSVILLE ELEMENTARY SCHOOL

Architect: Community Tectonics

Contractor: Shankle-Lind, LLC

Scope:  Addition and Renovation 9 classrooms and P.E. Room

Capacity:  435

Space/Student: N/A

Area:  19,557 sq. ft. addition

Total Cost:  $1,551,966.00

Cost/Square Foot:  $79.35

Completion:  January 2001

 

§      GRA-MAR MIDDLE SCHOOL

Architect: McFarlin Huitt Panvini

Contractor: Shankle-Lind, LLC

Scope:  42 Classrooms and Gym

Capacity:  832

Space/Student: 119.9 sq. ft.

Area:  99,759 sq. ft.

Total Cost:  $6,700,423.00

Cost/Square Foot:  $67.17 (includes new and renovation sq. ft.)

Completion:  August 2001

§      GRANBERY ELEMENTARY SCHOOL

Architect: Adkisson Harrison Architects

Contractor: B&C Contracting

Scope:  Addition 10 classrooms, P.E, Office improvements, Music and Art

Capacity:  553

Space/Student: N.A.

Area:  32,548 sq. ft. addition

Total Cost: $2,257,423.00

Cost/Square Foot:  $69.36 

Completion:  August 1999

 

§      ALEX GREEN ELEMENTARY SCHOOL

Architect: Moody/ Nolan Ltd.

Contractor: Tri-Star Construction

Scope: Addition and Remodel

Capacity: 400

Space/Student: 147 sq. ft.

Area: Additional 17,000 sq. ft.   

Total Cost: $1,955,070

Cost/Square Foot: $104.00

Completion: February 2004 

 

§      JULIA GREEN ELEMENTARY SCHOOL

Architect: Fowlkes & Associates

Contractor: Robert S. Biscan Company

Scope:  Addition 9 classrooms, PE Room, Office, Art, Music, Library, and Renovations

Capacity:  454

Space/Student: N/A

Area:  25,802 sq. ft.

Total Cost: $2,229,904.00

Cost/Square Foot:  $86.42

Completion:  July 2000

 

§     HAYNES MIDDLE HEALTH/MEDICAL SCIENCE DESIGN CENTER SCHOOL

Architect: McFarlin Huitt Panvini

Contractor: Robert S. Biscan Company

Scope: New Middle School

Capacity: 600

Space/Student: 135 sq. ft.

Area: 81,092

Total Cost: $6,061,186

Cost/Square Foot: $74.74

Completion: July 2003

 

§      HEAD MIDDLE MAGNET SCHOOL

Architect: Gobbell Hays Partners

Contractor: Alexander & Shankle

Scope:  Renovation and Addition (30 Classrooms and Gym)

Capacity:  562

Space/Student: 117 sq. ft.

Area:  65,873 sq. ft.

Total Cost:   $5,108,325.65

Cost/Square Foot:  $61.40

Completion:  November 2002

 

§      H.G. HILL MIDDLE SCHOOL

Architect: Badger & Associates, Architects

Contractor: Walter Harmon Construction, Incorporated

Scope:  Addition and Renovation (35 Classrooms and gym)

Capacity:  585

Space/Student: 146 sq. ft.

Area:  85,645 sq. ft.

Total Cost:  $5,526,779.08

Cost/Square Foot:  $64.53 (includes new and renovation sq. ft.)

Completion:  August 2000

 

§      HICKMAN ELEMENTARY SCHOOL

Architect: Orr/Houk & Associates

Contractor: Robert S. Biscan Company

Scope: New Building 37 classrooms and P.E.

Capacity:  593

Space/Student: 120.5 sq. ft.

Area:  71,466 sq. ft.

Total Cost:  $4,857,139.00

Cost/Square Foot:  $68.03

Completion:  August 2000

 

§      CORA HOWE ELEMENTARY SCHOOL

Architect: SSOE, Inc.

Contractor: McPherson/Shaw Incorporated

Scope:  New Library and Renovation in existing building

Capacity:  375

Space/Student: N/A

Area:  51,265 sq. ft.

Total Cost:  $645,510.00

Cost/Square Foot:  $12.66

Completion:  August 1999


§         A.Z. KELLEY ELEMENTARY SCHOOL

Architect: Gobbell Hayes Partners, Inc.

Contractor: Carden Company

Scope:  New Building

Capacity:  600

Space/Student: 128 sq. ft.

Area:  77,039 sq. ft.

Total Cost:  $6,779,362

Cost/Square Foot:  $88.00

Completion:  August 2006

 

§      JOHN F. KENNEDY MIDDLE SCHOOL

Architect: Hart Freeland Roberts

Contractor: R.G. Anderson Company

Scope:  New Building

Capacity:  932

Space/Student: 123 sq. ft.

Area:  114,620 sq. ft.

Total Cost:  $9,340,095.00

Cost/Square Foot:  $81.48

Completion:  August 2001

 

§      LOCKELAND ELEMENTARY DESIGN CENTER SCHOOL 

Architect: Adkisson Harrison Architects

Contractor: Robert S. Biscan Company

Scope: Renovate existing building.

Capacity: 400

Space/Student: 100 sq. ft.

Area: 40,183 sq. ft.

Total Cost: $2,014,185.00

Cost/ Square Foot: $50.12

Completion: May 2003

 

§      RUBY MAJOR ELEMENTARY SCHOOL

Architect: Thomas, Miller & Partners

Contractor: Robert S. Biscan Company

Scope: New Building

Capacity: 600

Space/Student: 113.9 sq. ft.

Area: 68,342 sq. ft.

Total Cost: $6,301,787.75

Cost/Square Foot: $92.21

Completion: March 2005

 

§      MARGARET ALLEN MIDDLE SCHOOL

Architect: E&H Architects, P.C.

Contractor: Shankle-Lind, LLC

Scope:  New Building

Capacity:  562

Space/Student: 139.8 sq. ft.

Area:  78,580 sq. ft.

Total Cost:  $5,973,000.00

Cost/Square Foot:  $76.02

Completion:  August 2002


§         THURGOOD MARSHALL MIDDLE SCHOOL

Architect: Jack Freeman & Associates

Contractor: Shankle-Lind, LLC

Scope:  New Building

Capacity:  1000

Space/Student: 113.5 sq. ft.

Area:  113,519 sq. ft.

Total Cost:  $11,048,457

Cost/Square Foot:  $97.35

Completion:  July 2006

 

§      HENRY MAXWELL ELEMENTARY SCHOOL

Architect: Orr-Houk

Contractor: Robert S. Biscan Company

Scope:  New Building (28 Classrooms and PE)

Capacity:  514

Space/Student: 125 sq. ft.

Area:  64,350 sq. ft.

Total Cost:  $4,807,082.00

Cost/Square Foot:  $74.70

Completion:  August 2001

 

§      MCKISSACK MIDDLE PROFESSIONAL DEVELOPMENT DESIGN CENTER SCHOOL

Architect: McKissack & McKissack

Contractor: Shankle-Lind, LLC

Scope:  Renovations and Additions (36 Classrooms and Gym)

Capacity:  607

Space/Student: 189 sq. ft. 

Area:  115,000 sq. ft. 

Total Cost:  $6,303,822.29

Cost/Square Foot: 54.82

Completion:  August 2002

 

§      MEIGS MAGNET MIDDLE SCHOOL

Architect: Gilbert McLaughlin Architects

Contractor: R.G. Anderson Company

Scope: New Building

Capacity: 625

Space/Student: 128 sq. ft.

Area: 83,315 sq. ft.    

Total Cost: $7,348,112

Cost/Square Foot: $88.20

Completion: May 2004 

 

§      DAN MILLS ELEMENTARY SCHOOL

Architect: Street Dixon Rick Architecture

Contractor: R.G. Anderson Company

Scope:  New Building

Capacity:  593

Space/Student: 124.5 sq. ft. 

Area:  73,807 sq. ft.

Total Cost:  $5,604,000

Cost/Square Foot:  $75.93

Completion:  August 2000

 

§      NAPIER ENHANCED OPTION ELEMENTARY SCHOOL

Architect: Moody/Nolan Ltd., Incorporated

Contractor: Branch Construction Company

Scope:  New Building (Enhanced Option)

Capacity:  499

Space/Student: 150.6 sq. ft.

Area:  75,145 sq. ft.

Total Cost:  $5,693,000.00

Cost/Square Foot:  $75.76

Completion:  August 2000

 

§      NASHVILLE SCHOOL OF THE ARTS TO MOVE INTO LEASED FACILITIES AT TENNESSEE PREPARATORY SCHOOL

Architect: SSOE, Incorporated

Contractor: Metropolitan Nashville Public Schools Maintenance Department

Scope: Renovate the leased facility to comply with current codes (ADA and Life Safety), build walls in open area, install air conditioning in formerly vocational spaces, build dance floors, and pave for parking.

Total Cost: $500,000

Completion: August 2003

 

§      NEELY’S BEND MIDDLE SCHOOL

Architect: Southeast Venture, LLC

Contractor Phase I: R.G. Anderson Company

Contractor Phase II: Shankle-Lind, LLC

Scope Phase I: Addition/Cafeteria Expansion (18 Classrooms)

Scope Phase II: Renovate, Admin. Space Expansion

Capacity: 768

Space per Student: 176 sq. ft.

Area: 29,115 sq. ft.

Total Cost Phase I: $2,271,450

Total Cost Phase II: $2,372,017

Cost per Square Foot Phase I: $78.02

Cost per Square Foot Phase II: $81.47  

Completion Phase I: March 2004

Completion Phase II: May 2006


§      OLD CENTER ELEMENTARY SCHOOL

Architect: Southeast Venture, LLC

Contractor: Robert S. Biscan Co.

Scope: Renovations and additions (New Library, Office & PE Room)

Capacity: 300

Space per Student: 164 sq. ft.

Area: 49,176 sq. ft.

Total Cost: $3,185,321

Cost per Square Foot: $64.77

Completion: August 2005

 

§      W.H. OLIVER MIDDLE SCHOOL

Architect: Jack Freeman & Associates

Contractor: Alexander & Shankle

Scope: New Middle School

Capacity: 700

Space/Student: 127.7 sq. ft.

Area: 89,392 sq. ft.

Total Cost: $8,966,953.00

Cost/Square Foot: $100.31

Completion: December 2004

  

§      PARAGON MILLS ELEMENTARY SCHOOL

Architect: Melvin Gill & Associates

Contractor: Kerry G. Campbell

Scope: Six classrooms and P.E. Room

Capacity:  474

Space/Student: N/A

Area:  15,700 sq. ft.

Total Cost:  $1,175,366.00

Cost/Square Foot:  $74.86

Completion:  December 2000

 

§      PARK AVENUE ENHANCED OPTION ELEMENTARY SCHOOL

Architect: Gould Turner Group Architecture

Contractor: R.G. Anderson Company

Scope:  New (Enhanced Option)

Capacity:  741

Space/Student:  171.5 sq. ft.

Area: 103,000 sq. ft.

Total Cost:  $7,192,069.02

Cost/Square Foot:  $69.83

Completion: August 1999

 

§      P.E. ROOMS - FOUR ELEMENTARY SCHOOLS

Cole, Haywood, Tom Joy, and Tusculum Elementary Schools

Architect: Hastings Architecture

Contractor:  Southeast Contractors

Scope: Additional Air Conditioned P.E. Rooms and Toilet facilities to 4 schools (see above)

Area per School: 6,910 sq. ft.

Total Cost for 4 P.E. Rooms: $2,010,355.91

Cost/ Square Foot: $73.49

Completion: All projects completed by October 2003

 

§      P.E. ROOMS - FOUR ELEMENTARY SCHOOLS

Pennington, Chadwell, Hermitage, and Neely’s Bend Elementary

Architect: Hastings Architecture

Contractor: Alexander & Shankle

Scope: Additional Air Conditioned P.E. Rooms and Toilet facilities to 4 schools (see above)

Area per School: 6,910 sq. ft.

Total Cost for 4 P.E. Rooms: $2,393,426.29

Cost/ Square Foot: $73.49

Completion: All projects completed by October 2003

 

§      P.E. ROOMS – TWO ELEMENTARY SCHOOLS

Lakeview Elementary and Una Elementary

Architect: Hastings Architecture

Contractor: Alexander & Shankle

Scope: Additional Air Conditioned P.E. Rooms and Toilet facilities for 2 schools (see above)

Area per School: 6,910 sq. ft.  

Total Cost for 2 P.E. Rooms: $1,249,000.00 

Cost per Square Foot: $87.15

Completion: September 2004

 

§      PERCY PRIEST ELEMENTARY SCHOOL

Architect: Fowlkes & Associates

Contractor: Alexander & Shankle

Scope:  Eight classrooms and P.E. Room and office renovation

Capacity:  474

Space/Student: N/A

Area:  18,794 sq. ft addition

Total Cost:  $1,553,646.88

Cost/Square Foot:  $82.67

Completion:  January 2001
 

§      ROSEBANK ELEMENTARY SCHOOL

Architect: Gilbert McLaughlin Architects

Contractor: Robert S. Biscan Company

Scope: Addition 14 classrooms and P.E.

Capacity:  534

Space/Student: N/A

Area:  24,435 sq. ft.

Total Cost:  $2,462,000.00

Cost/Square Foot:  $100.76

Completion:  August 2000

 

§      M.W. SHAYNE ELEMENTARY SCHOOL

Architect: E&H Architect, P.C.

Contractor: Alexander & Shankle

Scope: New Elementary School

Capacity: 600

Space/Student: 117 sq. ft.

Area: 70,225 sq. ft.

Total Cost: $5,209,059

Cost/Square Foot: $74.18

Completion: August 2004


 

§      STANFORD ELEMENTARY SCHOOL

Architect: Everton Oglsby Architects

Contractor: Alexander & Shankle

Scope:  New Building

Capacity:  415

Space/Student: 131 sq. ft.

Area:  54,470 sq. ft.

Total Cost:  $3,790,700.00

Cost/Square Foot:  $69.59

      Completion:  August 2002

 

§      SYLVAN PARK PAIDEIA DESIGN CENTER ELEMENTARY SCHOOL

Architect: Binkley Garcia Architecture, LLC

Contractor: Alexander & Shankle

Scope: Renovation and Addition

Capacity: 450

Space/Student: 128 sq. ft.

Area: 57,732 sq. ft.

Total Cost: $3,533,244

Cost/Square Foot: $33.75

Completion: July 2003

 

§      MARTHA VAUGHT MIDDLE SCHOOL 

Architect: Tuck Hinton Architecture

Contractor: R.G. Anderson Company

Scope: New Building

Capacity: 500

Space/Student: 138 sq. ft.

Area: 69,000 sq. ft.

Total Cost: $5,598,126.00

Cost/Square Foot: $81.13

Completion: June 2003

 

§      MT. VIEW ELEMENTARY SCHOOL

Architect: Thomas Miller Partners

Contractor: Roberts S. Biscan Company

Scope:  New Building

Capacity:  830

Space/Student: 103.75 sq. ft.

Area:  86,110 sq. ft.

Total Cost:  $6,370,000.00

Cost/Square Foot:  $74.07

Completion:  August 1999 

 

§      WARNER ENHANCED OPTION ELEMENTARY SCHOOL

Architect: R, Chris Magill Architects

Contractor: Robert S. Biscan Company

Scope: Modernization

Capacity: 400

Space/Student: 217 sq. ft.

Area: 87,000 sq. ft.

Total Cost: $3,970,000

Cost/Square Foot: $45.63

Completion: July 2004

 

§      WESTMEADE ELEMENTARY SCHOOL

Architect: Hastings Architecture

Contractor: R.G. Anderson Company

Scope: Addition 14 classrooms and P.E.

Capacity:  415

Space/Student: N.A.

Area:  21,111 sq. ft. addition

Total Cost:  $1,450,008.00

Cost/Square Foot:  $68.68

Completion:  April 1998

 

§      WHITSITT ELEMENTARY SCHOOL

Architect: Davis Stokes Chilton

Contractor: Alexander & Shankle Incorporated

Scope:  New Building

Capacity:  534

Space/Student: 126 sq. ft.

Area:  67,300 sq. ft.

Total Cost:   $5,292,000.00

Cost/Square Foot:  $78.63

Completion: December 1999

 

§      WRIGHT MIDDLE SCHOOL

Architect: Facilities Design Group, Incorporated

Contractor: Alexander & Shankle

Scope:  Addition 18 classrooms

Capacity:  1,135

Space/Student: N/A

Area:  24,850 sq. ft.

Total Cost:  $1,995,320.00

Cost/Square Foot:  $80.29

Completion:  August 2000

GLENGARRY ELEMENTARY SCHOOL

Architect: Facilities Design Group, Incorporated

Contractor: Alexander & Shankle

Scope:  Addition 18 classrooms

Capacity:  1,135

Space/Student: N/A

Area:  24,850 sq. ft.

Total Cost:  $1,995,320.00

Cost/Square Foot:  $80.29

Completion:  August 2000





      return to top