History of Projects
 


Color Construction Logo.JPGCOMPLETED CAPITAL IMPROVEMENT PROJECTS 1997-06


§       ADA COMPLIANCE

West End Middle, Hume Fogg High, M.L. King Magnet, Pearl-Cohn High 

Architect: Larry Woods & Associates

Contractor: Shankle-Lind, LLC

Scope: Bring Schools to ADA Compliant

Total Cost: $5,624,793
Completion: November 2004

§        ADA IMPROVEMENTS AT ADMINISTRATION BUILDING

Architect: Larry Woods & Associates

Contractor: SES Construction, LLC

Scope: Admin. Building ADA Compliance

Total Cost: $864,082

Completion: April 2006

 

§       AIR CONDITION MIDDLE SCHOOL GYMS (6 SCHOOLS)

Antioch Middle, Donelson Middle, Kennedy Middle, McMurray Middle, Two Rivers Middle, and Wright Middle

Engineer: NJC, Incorporated

Contractor: Anderson Piping

Scope: Install air conditioning systems in Gyms

Total Cost: $599,189

Completion: August 2003

§        AIR CONDITION MIDDLE SCHOOL GYMS PKG. "B"(3 SCHOOLS)
H.G. Hill, Brick Church, and Dalewood Middle Schools

Engineer: 3-D Engineering

Contractor: Advanced Mechanical

Scope: Install air conditioning systems in Gyms

Total Cost: $488,000

Completion: September 2005

 

§      AMQUI ELEMENTARY SCHOOL

Architect: Oxford Architecture

Contractor: Shankle-Lind, LLC

Scope:  New Building

Capacity:  652

Space/Student: 122.25 sq. ft.

Area:  79,708 sq. ft.

Total Cost:  $6,118,000.00

Cost/Square Foot:  $76.76

Completion:  September 2000

§      ANTIOCH MIDDLE SCHOOL

Architect: R. Chris Magill

Contractor: Price-Davis Construction, Inc.

Scope:  Modernization

Capacity:  809

Space/Student: 164

Area:  132,476 sq. ft.

Total Cost:  $1,113,335.75

Cost/Square Foot: $8.40

Completion: August 2000


§     
BAILEY MIDDLE SCHOOL

Architect: Maxwell Johanson Maher

Contractor: Robert S. Biscan Company

Scope:  Modernization and addition (24 classrooms)

Capacity:  719

Space/Student: 135 sq. ft.

Area:  97,000 sq. ft.

Total Cost:  $5,663,000.00

Cost/Square Foot: $58.38

Completion:  August 2001

§      JERE BAXTER MIDDLE SCHOOL

Architect: Southeast Venture

Contractor: R.G. Anderson Company

Scope: Addition/Cafeteria Expansion (12 Classrooms)

Capacity: 756

Space per Student: 148 sq. ft.

Area: 21,658 sq. ft.

Total Cost: $1,799,000

Cost per Square Foot: $83.00

Completion: March 2004

§      BELLSHIRE ELEMENTARY DESIGN CENTER SCHOOL

Architect: Hastings Architecture

Contractor: J. Harold Shankle Company

Scope: Addition 15 classrooms and P.E.

Capacity:  514

Space/Student: N.A.

Area:  24,165 sq. ft. addition

Total Cost:  $1,482,688.00

Cost/Square Foot: $61.36

Completion:  June 1998

 

§      BORDEAUX ENHANCED OPTION SCHOOL

Architect: Pitts & Associates

Contractor: R.G. Anderson Company

Scope: Addition and Renovation (19 classrooms, P.E. Room, and Kitchen addition)

Capacity: 300

Space/Student: 212.5 sq. ft.

Area: 63,744 sq. ft.

Total Cost: $2,986,000

Cost/Square Foot: $10.49

Completion: November 2004

 

§      BRICK CHURCH MIDDLE SCHOOL

Architect: E&H Architects, P.C.

Contractor: Robert S. Biscan Company

Scope:  New Building

Capacity:  652

Space/Student: 138 sq. ft.

Area:  89,830 sq. ft.

Total Cost:  $7,350,000.00

Cost/Square Foot:  $81.84

Completion:  August 2001

 

§      BROOKMEADE ELEMENTARY SCHOOL

Architect: Community Tectonics

Contractor: Mirsaidi Construction

Scope:  Addition and Renovation 11 classrooms and P.E. Room

Capacity:  375

Space/Student: N/A

Area:  20,662 sq. ft. addition

Total Cost:  $1,797,945.00

Cost/Square Foot:  $87.00

Completion:  January 2001

 

§      BUENA VISTA ENHANCED OPTION ELEMENTARY SCHOOL

Architect: Hinson Miller Kickirillo

Contractor: Robert S. Biscan Company

Scope: Addition and Renovation

Capacity: 400

Space/Student: 163 sq. ft.

Area: 65,355 sq. ft.

Total Cost: $4,191,000

Cost/Square Foot: $64.13

Completion: October 2003


§         CALDWELL ELEMENTARY SCHOOL

Architect: Community Tectonics

Contractor: Shankle-Lind, LLC

Scope: Addition and Renovation

Capacity: 600

Space/Student: 104 sq. ft.

Area: 62,212 sq. ft.

Total Cost: $3,975,158

Cost/Square Foot: $634.90

Completion: August 2005

 

§      CAMERON MIDDLE SCHOOL

Architect: Kline Swinney Associates

Contractor: Robert S. Biscan Company

Scope: Modernize existing building

Capacity: 850

Space/Student: 148 sq. ft.

Area: 125,699 sq. ft.

Total Cost: $4,237,000

Cost/Square Foot: $33.70

Completion: August 2003 

 

§      CARTER LAWRENCE ELEMENTARY MAGNET SCHOOL

Architect: Facilities Design Group

Contractor: Robert S. Biscan Company

Scope: New Elementary School

Capacity: 500

Space/Student: 131 sq. ft.

Area: 65,800 sq. ft.

Total Cost: $5,574,679

Cost/Square Foot: $84.72

Completion: July 2004

 

§      CHARLOTTE PARK ELEMENTARY SCHOOL

Architect: Larkin Group

Contractor: Alexander & Shankle

Scope:  Add 10 classrooms and PE Room, Renovate offices

      Capacity:  688 (Total School)

      Space/Student: N/A

      Area:  21,000sq. Ft.

      Total cost:  $1,350,962.00

      Cost/Square Foot:  $75.05

Completion:  January 2003


§         I.T. CRESSWELL ARTS MAGNET MIDDLE SCHOOL

Architect: Hastings Architecture Associates

Contractor: Robert S. Biscan Company

Scope: New Arts Magnet Middle School

Capacity: 600

Space/Student: 184 sq. ft.

Area: 110,405 sq. ft.

Total Cost: $10,729,675

Cost/Square Foot: $97.18

Completion: July 2006

 

§      CROFT MIDDLE DESIGN CENTER SCHOOL

Architect: Gould Turner Group Architecture

Contractor: Robert S. Biscan Company

Scope: New Middle School

Capacity: 800

Space/Student: 138 sq. ft.

Area: 110,000 sq. ft.

Total Cost: $8,609,053

Cost/Square Foot: $78.26

Completion: July 2003

 

§      DALEWOOD MIDDLE SCHOOL

Architect: Hastings Architecture

Contractor: Robert S. Biscan Company

Scope:  Renovation and Addition (49 Classrooms and Gym)

Capacity:  832

Space/Student: 130.72 sq. ft.

Area:  109,000 sq. ft.

Total Cost:  $6,646,652.00

Cost/Square Foot:  $60.98

Completion:  July 2002 

 

§      DONELSON MIDDLE SCHOOL

Architect: Gresham Smith & Partners

Contractor: Alexander & Shankle

Scope: Addition/Renovation (43 Classrooms and Gym)

Capacity:  742

Space/Student: 151.6 sq. ft.

Area:  112,489 sq. ft.

Total Cost:  $6,163,367.00

Cost/Square Foot:  $54.79 (includes new and renovation sq. ft.)

Completion:  November 2000

 

§      DUPONT ELEMENTARY SCHOOL

Architect: Pitts & Associates

Contractor: Romach, Incorporated

Scope: Addition 6 classrooms and P.E./office

Capacity: 454

Space/Student: N/A

Area: 16,000 Sq. Ft. additions

Total Cost:  $1,096,000.00

Cost/Square Foot:  $68.50

Completion:  March 2000


§         DUPONT HADLEY MIDDLE SCHOOL

Architect: Fowlkes & Associates

Contractor: Robert S. Biscan Company

Scope: Addition & Renovation

Capacity: 600

Space/Student: 177 sq. ft.

Area: 106,348

Total Cost:  $3,100,000

Cost/Square Foot:  $29.15

Completion:  May 2005

 

§         EAKIN ELEMENTARY SCHOOL

Architect: Earl Swensson Assoc.

Contractor: Shankle-Lind, LLC

Scope: Addition & Renovation

Capacity: 500

Space/Student: 207 sq. ft.

Area: 103,730

Total Cost:  $9,366,130

Cost/Square Foot:  $90.29

Completion:  October 2006

 

§      JOHN EARLY MIDDLE PAIDEIA MAGNET SCHOOL

Architect: Thompson Architectural Group

Contractor: Medical Construction Group

Scope:  New Building

Capacity:  629

Space/Student: 146 sq. ft.

Area:  91,989 sq. ft.

Total Cost:  $6,809,000.00

Cost/Square Foot:   $74.02

Completion:  July 2002

 

§      CONVERT OLD JOHN EARLY BUILDING TO MCGRUDER FAMILY RESOURCE CENTER

Architect: Adkisson Harrison & Associates

Contractor: Metropolitan Nashville Public Schools Maintenance Department

Scope:  Replace broken windows, install carpet, bring building up to current codes, repair water damage, and paint throughout.

Total Cost: $250,000

Completion: August 2003 

 

§      EAST LITERATURE MAGNET SCHOOL

Architect: Street Dixon Rick Architecture

Contractor: Doster Construction Company

Scope: Modernization

Capacity: 1,300

Space/Student: 160 sq. ft.

Area: 208,300 sq. ft.

Total Cost: $8,216,180

Cost/Square Foot: $39.44

Completion: August 2004


§         EAST LITERATURE MAGNET ATHLETIC FIELD

Architect: SSOE, Inc.

Contractor: Bruce Adams Construction

Scope: Rough grading athletic field

Total Cost: $638,276

Completion: September 2005

 

§      THOMAS A. EDISON ELEMENTARY SCHOOL

Architect: E&H Architects, P.C.

Contractor: Turner Universal

Scope: New Elementary School

Capacity: 600

Space/Student: 117 sq. ft.

Area: 70,225 sq. ft.

Total Cost: $7,197,301

Cost/Square Foot: $102.48

Completion: July 2004

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS (2 SCHOOLS)

Granbery Elementary and Andrew Jackson Elementary

Architect: Adkisson Harrison & Associates

Contractor: Bruce Adams Construction

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $593,000.00

      Completion: August 2003


§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

      JT Moore Middle

Architect: SSOE, Incorporated

Contractor: R.G. Anderson Company

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $540,775.00

Completion: August 2003

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

      Kings Lanes Design Center

Architect: SSOE, Incorporated

Contractor: CSMC, Incorporated

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $322,052.00

Completion: August 2003 

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

DuPont Hadley Middle School

Architect: Hastings Architecture

Contractor: Bruce Adams Construction

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $97,000.00

Completion: August 2003

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

Dodson Elementary and Apollo Middle

Architect: Hastings Architecture

Contractor: Bruce Adams Construction

Scope: Construct walls at open pods and other open areas to create classrooms

Total Cost: $200,299.00

Completion: August 2003

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

Fall Hamilton

Architect: Adkisson Harrison & Associates

Contractor: CSMC, Incorporated

Scope: Construct walls at open areas to create classrooms.

Total Cost: $1,167,318

Completion: June 2004

 

§      ENCLOSE CLASSROOMS IN OPEN CONCEPT AREAS

Glencliff Elementary

Architect: Hastings Architecture

Contractor: RCR Building Corporation

Scope: Construct walls at open areas to create classrooms.

Total Cost: $1,058,391

Completion: June 2004

 

§      FALL HAMILTON ENHANCED OPTION ELEMENTARY SCHOOL

Architect: The Larkin Group

Contractor: Shankle-Lind, LLC

Scope: Addition 10 classrooms and PE

Capacity:  314

Space/Student: N/A

Area:  23,000 sq. ft.

Total Cost:  $1,655,000.00

Cost/Square Foot:  $71.96

Completion:  June 2000

 

§      GLENDALE ELEMENTARY SCHOOL 

Architect: Barge Waggoner Sumner & Cannon

Contractor: R.G. Anderson Company

Scope: Addition and Modernization

Capacity: 400

Space/Student: 130 sq. ft.

Area: 28,900 existing, 23,000 new sq. ft.

Total Cost: $3,127,000

Cost/Square Foot: $60.13

Completion: July 2004

 

§      GLENGARRY ELEMENTARY SCHOOL

Architect: SSOE, Incorporated

Contractor: Fitzgerald Construction

Scope: Addition (6 classrooms, PE Room, and Kitchen Addition)

Capacity: 300

Space/Student: 83.33 sq. ft.

Area: 25,000 sq. ft.

Total Cost: $1,596,643

Cost/Square Foot: $63.87

Completion: July 2004


§         GLENVIEW ELEMENTARY SCHOOL

Architect: Hart Freeland Roberts

Contractor: R.G. Anderson Co. Inc.

Scope: New Building

Capacity: 500

Space/Student: 134 sq. ft.

Area: 67,000 sq. ft.

Total Cost: $7,009,061

Cost/Square Foot: $97.96

Completion: August 2006

 

§      GOODLETTSVILLE ELEMENTARY SCHOOL

Architect: Community Tectonics

Contractor: Shankle-Lind, LLC

Scope:  Addition and Renovation 9 classrooms and P.E. Room

Capacity:  435

Space/Student: N/A

Area:  19,557 sq. ft. addition

Total Cost:  $1,551,966.00

Cost/Square Foot:  $79.35

Completion:  January 2001

 

§      GRA-MAR MIDDLE SCHOOL

Architect: McFarlin Huitt Panvini

Contractor: Shankle-Lind, LLC

Scope:  42 Classrooms and Gym

Capacity:  832

Space/Student: 119.9 sq. ft.

Area:  99,759 sq. ft.

Total Cost:  $6,700,423.00

Cost/Square Foot:  $67.17 (includes new and renovation sq. ft.)

Completion:  August 2001

§      GRANBERY ELEMENTARY SCHOOL

Architect: Adkisson Harrison Architects

Contractor: B&C Contracting

Scope:  Addition 10 classrooms, P.E, Office improvements, Music and Art

Capacity:  553

Space/Student: N.A.

Area:  32,548 sq. ft. addition